REMOVAL OF ASBESTOS CONTAINING MATERIALS

3 – REMOVAL OF ASBESTOS CONTAINING MATERIALS
3.1 – REMOVAL OF ASBESTOS CONTAINING MATERIALS CRUMBLY
INSIDE AND OUTSIDE OF A BUILDING
For the removal of friable asbestos is important that You are aware
of the process to which you are an actor.
We will proceed with the preparation / provision of :
3.1.1 yard work ;
3.1.2 confinement (confinement static , dynamic confinement /
air extractors ), high-efficiency HEPA filters ( capture of the fibers ) ;
3.1.3 Testing of the yard ( leak test) ;
3.1.4 area decontamination of personnel and materials.
The first includes : local pristine ( for dressing
workers ) , shower room ( for the decontamination of the worker) ,
local equipment (local undressing of
worker contaminated ), the second includes: local washing ,
local packing and local temporary storage
pending removal ;
3.1.5 Cleaning procedures of personnel;
3.1.6 techniques and procedures to carry out the removal of material
containing asbestos;
3.1.7 Procedures for decontamination of the site;
3.1.8 Packaging and labeling of waste ( for their removal
from the site ) ;
3.1.9 Environmental Monitoring ;
3.1.10 Certification  local reclaimed ;
3.1.11 protection of workers.
Part Two – Work Practices
3.1.1 – Yard work
The installation of site remediation involves the preparation
of work enclosure and enclosure; electricity connections
and hydraulic placement of equipment and devices, and signs ;
temporary works , electrical and lighting environments
damp escape systems that do not compromise the isolation
of the contaminated area , the filtering device for water showers and
of the decontamination of waste, decontamination units of
staff . The site is designed and then prepared according to the
removal operations
_ Remember that:
Before starting work, you must get the necessary information from
Head to your site that has the task of monitoring and coordination
of the various activities .
The procedures and the evacuation route were studied preliminarily
in the elaboration of the WORK PLAN to avoid contaminate the external environment or the inhabited areas of the building.

Cantiere Amianto

Rispondi

Inserisci i tuoi dati qui sotto o clicca su un'icona per effettuare l'accesso:

Logo di WordPress.com

Stai commentando usando il tuo account WordPress.com. Chiudi sessione /  Modifica )

Foto Twitter

Stai commentando usando il tuo account Twitter. Chiudi sessione /  Modifica )

Foto di Facebook

Stai commentando usando il tuo account Facebook. Chiudi sessione /  Modifica )

Connessione a %s...

Questo sito utilizza Akismet per ridurre lo spam. Scopri come vengono elaborati i dati derivati dai commenti.