Using a smoke generator, saturated confined space. Check that there is no release of smoke from confinement, where you encounter leaks sealed.
Turn on the extractors. The time of extraction, of the smoke, must be done in about 15 minutes. This fact must be respected to allow 4 air changes per hour.